'Level-off' cement plugging method to cure lost circulation …
The whole NPT due to the lost circulation was 31.5 h consisting of 0.5 h for preparation and waiting for program, 7 h for tripping of DP with RTTS (in and out of the hole), 1 h for setting and unsetting packers, 2 h for making cement slurry (following packer set), 0.5 h for pumping slurry and displacement, 20 h wait on cement and monitoring ...